Friends of St. Teresa Nzara Hospital Expansion – Update 29 April – 05 May 2019 Overview The Solid progress of last week carried over, with some delays on electrical work, plumbing proceeded. Tiling work continued at the Theatre and the Surgical Ward. The cement skirting that borders the three buildings were completed in preparation for… Continue reading Friends of St. Teresa Nzara Hospital Expansion – Update 29 April – 05 May 2019
Month: May 2019
Friends of St. Teresa Nzara Hospital Expansion- Blood Bank Update 29 April – 05 May 2019
Overview As of this week the veranda columns have been completed on three sides of the building, with 13 remaining to be casted. The lintel level tie beam was completed this week, allowing the final level of bricks to continue. Also the pouring of the veranda slab made progress and the excavation of the septic… Continue reading Friends of St. Teresa Nzara Hospital Expansion- Blood Bank Update 29 April – 05 May 2019